Now, the construction of two 2.4 km long tracks continues at the String Technology Testing Centre in Sharjah. Let's see, how these sites are progressing.
Track №2 with a flyover of trusses
— The installation of 46 intermediate supports with a span of 48 metres has been completed.
— On one of the anchor supports, the main construction has been completed, finishing work is underway.
— On the opposite anchor support, the pouring of the foundation and the lower level of the walls has been completed.
— Concrete and engineering works continue.
— Work is underway to connect electricity, which is scheduled for autumn 2022.
Concreting the walls of the anchor support of the track №2
Track №4 with an overpass of semi-rigid rails
— The installation of 8 intermediate supports with a span of 144 and 288 metres has been completed.
— Major construction work has bee completed on both anchor supports.
— Preparatory work is underway to erect the structure of the string-rail track.
— The installation of the anchor units on both anchor supports is being completed.
— Work is underway to connect electricity, which is scheduled for autumn 2022.
— The development and assembly of a new model of suspended urban passenger uPod U4-212-01 with a capacity of 25 people for track №4 has been completed.
Installation of a beam with variable stiffness on the anchor support of track №4